Masking ver 29 scope and plans
Masking ver 29 scope and plans
Sprint alias
Macaulay Culkin
Sprint goals
Masking Licensing by sizing
Sprint dates
Milestone | Date |
---|---|
Start date | Dec 26, 2023 |
Code freeze | Jan 19, 2024 |
End date | Jan 26, 2024 |
Capacity planning
Working days in sprint: 17
| People | Full capacity | Current sprint | Planned load | Planned load, % |
---|---|---|---|---|---|
Backend | 2 | 352 | 272 | 163 | 60% |
Frontend | 2 | 352 | 160 |
|
|
DBA | 1 |
|
|
|
|
QA | 2 | 352 | 312 | 112 | 36% |
Vacations, days off
| Days |
---|---|
@Andrew Shalimov | 11.12.23-25.12.23 |
@Aleksandra | 24.12.23-08.01.24 |
@Dima Urban (Unlicensed) | 26.12.23-29.12.23 |
Potential risks
Risk | Mitigation |
---|---|
too many days off | Reduce the scope of the sprint.
|
Tasks
, multiple selections available,
Related content
Masking ver 30 scope and plans
Masking ver 30 scope and plans
More like this
Masking service events
Masking service events
Read with this
Masking ver 32 scope and plans
Masking ver 32 scope and plans
More like this
Release 28.0
Release 28.0
Read with this
Masking ver 33 scope and plans
Masking ver 33 scope and plans
More like this
Accelario logging events policy
Accelario logging events policy
Read with this