Gadget | ||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
|
Sprint goals
Accelario Server Usage Statistics (UsageMate)
Start date 11/20/2023
Code freeze 12/15/2023
End date 12/26/2023
Capacity planning
Working days in sprint: 22
People | Full capacity | Current sprint | Planned load | Planned load, % | |
---|---|---|---|---|---|
Backend | 2 | 352 | 272 | 163 | 60% |
Frontend | 2 | 352 | 160 | ||
DBA | 1 | ||||
QA | 2 | 352 | 312 | 112 | 36% |
Vacations, day offs
Days | |
---|---|
11.12.23-25.12.23 | |
04.12.23-08.12.23 | |
29.11.23-01.12.23 |
Potential risks
Risk | Mitigation |
---|---|
Onboarding new frontend team member | Addition of a new frontend member could lead to a temporary reduction in the team's development velocity |
?? Tasks
https://accelario.atlassian.net/issues/?jql=project%20=%20%22IM%22%20and%20sprint%20=%2072%20and%20issuetype%20!=%20%22Epic%22%20and%20issuetype%20NOT%20IN%20subtaskIssueTypes()%20ORDER%20BY%20rank%20asc,%20key%20ASC,%20issuetype%20ASC,%20priority%20DESC,%20updated%20DESC