Sprint dates

Milestone

Date

Start date

09

Code freeze

27 Sep

End date

04

Capacity planning

Working days in sprint: 25

People

Full capacity

Current sprint

Planned

load

Planned

load, %

Backend

2

352

272

163

60%

Frontend

2

352

160

DBA

1

QA

1.5

252

80

54

65%

Vacations, days off

Andrew vacation

Days

26 August

Ukraine Independence day

19-30.08

Aleksandra vacation

19-30.08

Potential risks

Risk

Mitigation

...