Data anonymization ver 36 scope and plans

Data anonymization ver 36 scope and plans

Sprint alias

 

image-20240812-073934.png
Keanu Reeves

 

Sprint goals

  1. Masking job progress page

  2. Excel anonymization support

 

UI Design

 

Sprint dates

Milestone

Date

Milestone

Date

Start date

Sep 12, 2024

Code freeze

Oct 21, 2024

End date

Oct 28, 2024

Capacity planning

Working days in sprint: 25

 

People

Full capacity

Current sprint

Planned

load

Planned

load, %

 

People

Full capacity

Current sprint

Planned

load

Planned

load, %

Backend

2

352

 

132

37,5%

Frontend

1

176

 

85

48%

DBA

1

 

 

 

 

QA

1

176

 

100

57%

Vacations, days off

 

Days

 

Days

 

 

 

 

 

 

Potential risks

Risk

Mitigation

Risk

Mitigation

Tasks

 