Sprint goals
Accelario Server Usage Statistics (UsageMate)
Start date 11/20/2023
Code freeze 12/15/2023
End date 12/22/2023
Capacity planning
Working days in sprint: 22
People | Full capacity | Current sprint | Planned load | |
---|---|---|---|---|
Backend | 2 | 352 | 272 | |
Frontend | 2 | 352 | 160 | |
DBA | 1 | |||
QA | 2 |
Vacations, day offs
Days | |
---|---|
11.12.23-25.12.23 | |
04.12.23-08.12.23 | |
29.11.23-01.12.23 |
Potential risks
Risk | Mitigation |
---|---|
Onboarding new frontend team member | Addition of a new frontend member could lead to a temporary reduction in the team's development velocity |