Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 15 Current »

Sprint goals

  1. Accelario Server Usage Statistics (UsageMate)

Start date 11/20/2023

Code freeze 12/15/2023

End date 12/22/2023

Capacity planning

Working days in sprint: 22

People

Full capacity

Current sprint

Planned

load

Planned

load, %

Backend

2

352

272

163

60%

Frontend

2

352

160

DBA

1

QA

2

352

312

112

36%

Vacations, day offs

Days

Andrew Shalimov

11.12.23-25.12.23

Vladimir Garkusha

04.12.23-08.12.23

dmitry.zhigiliy

29.11.23-01.12.23

Potential risks

Risk

Mitigation

Onboarding new frontend team member

Addition of a new frontend member could lead to a temporary reduction in the team's development velocity

?? Tasks

https://accelario.atlassian.net/issues/?jql=project%20=%20%22IM%22%20and%20sprint%20=%2072%20and%20issuetype%20!=%20%22Epic%22%20and%20issuetype%20NOT%20IN%20subtaskIssueTypes()%20ORDER%20BY%20rank%20asc

  • No labels