Sprint alias

image-20240812-073934.png

Sprint goals

  1. Masking job progress page

  2. Excel anonymization support

UI Design

https://xd.adobe.com/view/7f475c84-ae10-4701-9ccc-1bc28a09b86e-2a14/

Sprint dates

Milestone

Date

Start date

Code freeze

End date

Capacity planning

Working days in sprint: 25

People

Full capacity

Current sprint

Planned

load

Planned

load, %

Backend

2

352

272

163

60%

Frontend

2

352

160

DBA

1

QA

1.5

252

80

54

65%

Vacations, days off

Days

Potential risks

Risk

Mitigation

?? Tasks

https://accelario.atlassian.net/issues/?jql=project%20%3D%20%22IM%22%20and%20fixVersion%20%3D%20%22Masking%2036.0%22%20and%20issuetype%20!%3D%20%22Epic%22%20and%20issuetype%20NOT%20IN%20subtaskIssueTypes()%20ORDER%20BY%20priority%2C%20Rank%20asc