Sprint dates
Milestone | Date |
---|---|
Start date | Jul 23, 2024 |
Code freeze | Aug 29, 2024 |
End date | Sep 5, 2024 |
Capacity planning
Working days in sprint: 25
| People | Full capacity | Current sprint | Planned load | Planned load, % |
---|---|---|---|---|---|
Backend | 2 | 352 | 272 | 163 | 60% |
Frontend | 2 | 352 | 160 |
|
|
DBA | 1 |
|
|
|
|
QA | 1.5 | 252 | 80 | 54 | 65% |
Vacations, days off
| Days |
---|---|
26 August | Ukraine Independence day |
19-30.08 | Aleksandra vacation |
|
|
Potential risks
Risk | Mitigation |
---|
Tasks